A wall panel arrives framed, sheathed and sometimes wrapped. The electrician and plumber still have to get through it. Done well, the wiring and pipes slot into planned routes; done badly, trades drill structure they should not and the engineer finds out at inspection. The difference is almost always a conversation that either happened before the layout was approved or did not.
What Changes With Panels, and What Does Not
In a site-framed house, the framers finish a floor, the trades arrive and the walls are still open for rough-in. With panels, the framing is done earlier and elsewhere, and the walls may be sheathed before any trade sees them. Rough-in itself does not disappear: wires still go through studs, drains still need slope, vents still need to reach the roof. What moves is the planning, because the best moment to decide where things go is before the panel is built.
Decisions to Make Before the Layout Is Approved
- ✓Which walls carry plumbing: drain and vent lines often need deeper or specially detailed walls, so flag them on the drawings early.
- ✓Where the main electrical panel, meters and service entrances land, so the shop can leave the right openings.
- ✓Which vertical chases and horizontal routes the trades want, and whether the shop drills holes or the trades do it.
- ✓Where plates, shear walls and braced walls limit what can be drilled or cut. Only the engineer can answer that for your project.
- ✓Whether windows, doors and wrap are installed in the shop or on site, since they change when each trade can start.
- ✓What gets labelled on the panel: stud bays, circuits or box locations are easier to find when the shop marks them.
Electrical: Permits, Licensing and Panel Routes
Electrical work in BC is overseen by Technical Safety BC, which states that a homeowner permit is often required for electrical installations or alterations and that you should check one is in place before work begins when you hire a licensed contractor (see Homeowner Electrical Permits, Technical Safety BC). It also notes that owners of stratas and non-strata duplexes cannot obtain homeowner permits, so a licensed contractor pulls the permit on those projects. Confirm the current rules and verify any contractor's licence with the regulator before you hire.
On the practical side, electrical contractors who do new-build wiring in Greater Victoria will want to see the panel and service locations, the box and fixture plan, and a decision on how wires reach the top plate and floor above before they quote. Giving them the panel layout drawings early lets them flag a problem while the shop can still adjust. For a plain-language walk through the permit side, this guide to the Technical Safety BC electrical permit is a useful companion.
Plumbing and Gas: Municipal Permits and Inspections
Plumbing is regulated differently. The Province describes the BC Plumbing Code as providing the technical requirements for the design, installation, alteration and repair of plumbing systems, applying to new construction, alterations and repairs (see BC Plumbing Code 2024, Province of British Columbia). Permits are handled by the local government. The City of Victoria, for example, requires plumbing permits for adding or removing fixtures and for installing or altering sewer or water services, and takes inspection requests through its online portal (Plumbing Permits, City of Victoria). Other municipalities set their own process, so check yours.
For the trade side, plumbing and gas contractors handle rough-in on new homes in the region; the useful question for a panelized job is which walls they need to see before the panel layout is final, and how they want the inspections sequenced with the framing. Gas work has its own rules, so ask your contractor which permits and inspections apply, and a quick gas permit checker can help you frame the question.
Sequencing the Inspections
- 1Framing and panel installation, including bracing and any engineer sign-off.
- 2Rough-in by each trade, with the walls still accessible for inspection where required.
- 3Inspections requested by the trades or the builder, as your municipality requires them.
- 4Insulation, vapour and air barrier work, and any Step Code testing, after rough-in passes.
- 5Closing in the walls.
Closed or sheathed panels can limit access, so ask your building department when it wants to see rough-in work and what access it needs. The schedule has to keep the inspection windows open, which is easiest when the trades, the shop and the builder have all seen the same drawings. A wall panel take-off is a good place to start the list of what is going where.
Delivery and Handling
Panels with wiring openings or plumbing detailing are handled like any other panels, but they should be labelled so the right wall lands in the right place. Plan the crane, access and storage with your supplier; our guide to coordinating foundations and panel delivery covers the foundation side, and the wall panel weight estimator gives a rough lift weight for the crane conversation.
Frequently Asked Questions
Can electricians and plumbers rough in after wall panels are installed?
Yes. Panels are framing, so the trades route wiring and pipes through them as they would any wall. The difference is planning chases and openings earlier and checking inspection access before the walls are closed.
Does the panel shop do the wiring and plumbing?
It depends on the scope. OG Prefab builds panels from your drawings; wiring and plumbing are normally done by licensed trades you or your builder hire. Confirm the scope in writing.
Who permits the electrical and plumbing work?
Electrical permits are handled through Technical Safety BC and plumbing permits through your local government. Your licensed contractors usually apply for them. Confirm the current process for your project.
Can trades drill through the panels?
Only where the engineer and the code allow. Holes through plates, studs in shear walls and other structural members need approval, so agree the routes before the panels are built.
What happens if a route is missed?
Ask the engineer before cutting. A missed route found early can be corrected in the shop or detailed on site with approval; one found after the walls are closed is a costly repair.