Prefab wall systems - also called wall panels, panelized framing, or off-site framing - are wall assemblies built in a controlled factory environment and delivered to the construction site ready to crane or lift into place. They replace the traditional process of measuring, cutting, and assembling walls piece by piece on site.
How the Prefab Framing Process Works, Step by Step
The prefab framing process moves work from the job site into a factory, but the order of events on a project is what makes it fast. Here is the sequence from drawings to a standing frame.
- 1Drawings and engineering. The structural drawings from your architect, designer, or engineer are the starting point. Panels are manufactured to the drawing, so the details need to be resolved before fabrication starts.
- 2Panel layout. The walls are broken into panels sized for transport and lifting, with openings for windows and doors located to the drawing.
- 3Foundation and fabrication run in parallel. Panels are built while the foundation is being prepared and poured, rather than waiting until the foundation is finished. See how much time this saves.
- 4Factory fabrication. Each panel is framed on a flat table or jig to a fixed tolerance, then sheathed (and in closed panels, insulated) before it leaves the shop.
- 5Numbering and loading. Panels are numbered and loaded onto trucks in installation sequence, so the crew is not sorting walls in the yard.
- 6Delivery and crane set-up. Panels arrive on a scheduled day, and the crane and crew are coordinated for that delivery. Access for the truck and crane is checked in advance.
- 7Stand, plumb, and brace. Panels are lifted onto the completed foundation, fastened, plumbed, and braced. A trained crew can stand the walls of a full storey in a single day, then move on to floor and roof framing.
- 8Dry-in. With the walls up fast, the roof structure follows and the building is closed in sooner, which limits how long lumber sits exposed to Victoria rain.
Prefab does not replace your general contractor, foundation, or engineer. It changes the framing stage. For the framing and foundation work we do, see our prefab wall systems service and framing service, or read how to choose a framing contractor.
Types of Prefab Wall Systems
| Panel Type | What It Is | Best For | Insulation |
|---|---|---|---|
| Open panel (stick) | Pre-framed walls, no sheathing | Standard residential builds | Filled on site (batt or spray) |
| Closed panel | Pre-framed + sheathed + insulated | High-performance builds | Factory-installed (batt or spray) |
| SIP (Structural Insulated Panel) | Foam core bonded between OSB skins | Passive house, Step Code builds | Continuous foam, no thermal bridging |
| Mass timber panel (CLT) | Cross-laminated solid timber | Commercial, multi-family, premium custom | Separate exterior insulation layer |
How Prefab Panels Are Made
- 1Structural drawings from your architect or designer are converted to panel fabrication files.
- 2A fabrication facility cuts lumber to precise dimensions using automated saws.
- 3Wall framing is assembled on a flat table - studs, plates, headers, and blocking all positioned to the drawing.
- 4Sheathing and sometimes insulation are applied and fastened to exact specification.
- 5Panels are numbered, stacked, and loaded onto flatbed trucks in installation sequence.
- 6Panels arrive on site ready to stand - typically installed in a day or two for a single-family home.
BC Energy Step Code and Prefab Panels
BC's Energy Step Code requires progressively better building envelope performance on new construction, with Step 5 (net-zero ready) as the end goal. Prefab closed panels and SIPs are well-suited to Step Code compliance because they can be engineered with precise, consistent insulation levels and airtight assembly details that are very difficult to achieve reliably with site framing.
What to Ask Your Builder About Prefab Panels
- ✓Which fabricator supplies your panels, and what is their quality certification?
- ✓Are panels delivered in installation sequence or does the crew need to sort on site?
- ✓Who is responsible for the engineering drawings used for fabrication?
- ✓What happens if a panel is fabricated incorrectly - what is the correction process?
- ✓Is the framing crew trained and experienced with panel installation?
Frequently Asked Questions
How does the prefab framing process work?
Walls are built as panels in a factory from your structural drawings, numbered in installation sequence, delivered to site, and lifted by crane onto the foundation, where they are fastened, plumbed, and braced. Fabrication happens while the foundation is being prepared, so the on-site framing stage is much shorter.
What is the difference between open and closed wall panels?
Open panels are pre-framed walls without sheathing, with insulation filled on site. Closed panels are framed, sheathed, and insulated before they leave the factory.
Do I still need a general contractor and engineer with prefab framing?
Yes. Prefab changes how the walls are framed, not who is responsible for the project. Panels are built to structural drawings, so an engineer or designer still produces them, and the rest of the build is coordinated as usual.