FRAMING · FOUNDATIONS · BC✦INSURED✦PREFAB WALL SYSTEMS✦FREE QUOTE IN 48 HRS✦778-403-6987✦INFO@OGPREFAB.COM✦FRAMING · FOUNDATIONS · BC✦INSURED✦PREFAB WALL SYSTEMS✦FREE QUOTE IN 48 HRS✦778-403-6987✦INFO@OGPREFAB.COM✦FRAMING · FOUNDATIONS · BC✦INSURED✦PREFAB WALL SYSTEMS✦FREE QUOTE IN 48 HRS✦778-403-6987✦INFO@OGPREFAB.COM✦FRAMING · FOUNDATIONS · BC✦INSURED✦PREFAB WALL SYSTEMS✦FREE QUOTE IN 48 HRS✦778-403-6987✦INFO@OGPREFAB.COM✦
Request a Quote→778-403-6987→
Free tool for builders

Foundation Excavation
Volume & Truckload Calculator

Estimate how much soil comes out of a house or garage foundation dig, how much it bulks up once it is loose, and roughly how many truckloads leave the site. Enter the footprint, the dig depth and the working room outside the footings. Read our guide to foundation excavation in Victoria BC for what happens before the pour, then size the pour itself with the foundation concrete calculator.

m

Outside of the footings.

m
m

From existing grade to the underside of the footings.

m

Space outside the footings for forms, damp-proofing and drains.

m : 1

Horizontal per 1 m of depth. 0 for vertical or shored sides. Your engineer or WorkSafeBC rules set this.

m
%

How much the soil bulks up once dug. Pick a preset or enter your own.

%

Backfill and landscaping that never leaves the lot.

m³

Loose volume per load. Ask your hauler.

Total dig (in the ground)
161.6 m³
about 211 cubic yards, 13.2 m x 10.2 m at the top
Hauled away (loose)
141.4 m³
about 185 cubic yards after 25% swell
Truckloads
18
at 8 m³ per load
Kept on site
48.5 m³
measured in the ground, for backfill and landscaping
Topsoil stripped
40.4 m³
part of the total dig, usually stockpiled for reuse
Request a Quote →Request a Quote

Estimate only. This is not an excavation plan, a shoring or sloping design, or a quote. Dig depth, side slopes and shoring are set by your drawings, your engineer and WorkSafeBC rules, and real swell depends on the material on your lot. Confirm truck capacity with your hauler. OG Prefab is a prefab wall panel, framing and foundation company serving builders, developers and homeowners directly. This tool does not produce a quote, and no pricing is implied.

Assumptions

  • The dig is a rectangle: the building footprint plus the working room you enter on every side, at the full depth you enter.
  • With a side slope above zero, each side lays back by that horizontal distance for every 1 m of depth, and the volume is worked out with the prismoidal formula, which is exact for this shape. Zero means vertical sides, as with shoring or a shallow cut.
  • Volumes are bank volumes (soil as it sits in the ground) until they are marked loose. Loose volume is bank volume increased by the swell percentage.
  • Swell presets come from US Army FM 5-434, Table 1-2: sand 10 to 15%, earth (loam or silt) 15 to 35%, gravel 25%, clay 40%. Where the table gives a range, the preset is the midpoint. Blasted rock and mixed fill are not preset; ask your excavator.
  • Topsoil is shown separately because it is usually stockpiled for landscaping. It is part of the total dig, not extra to it.
  • The share kept on site (for backfill and landscaping) is removed before trucking. Everything else is hauled loose. The default of 30% is a placeholder; your excavator decides what can be reused.
  • Truck capacity is a loose volume per load. The default of 8 m³ is a placeholder; capacity depends on the truck, the material and weight limits, so ask your hauler.

Sources

More Free Tools

Prefab vs. Stick-Built Calculator

Compare framing days and carrying costs between a prefab panel install and traditional stick framing on your project size.

Rain Delay Cost Calculator

Estimate what standing crew time and carrying costs could add up to while a stick-built frame sits open to the weather.

Build Timeline Estimator

Get a rough phase-by-phase schedule from permitting through handover, and see how framing method shifts the timeline.

Owner-Builder vs. GC Comparator

See how self-managed trade overruns and your own time stack up against a general contractor's markup.

Wall Panel Take-Off Estimator

Turn linear feet and wall height into wall area, a rough panel count and stud count before you send plans out.

Framing Material Take-Off

Rough studs, plates and sheathing sheets for a wall run, with a waste allowance you set.

Panel Delivery Load Planner

Estimate panels per truck load and the number of loads for your job, to start the delivery conversation.

Schedule Float Planner

Compare expected weather-lost days against the float in your schedule, using your own assumptions.

Wall Panel Weight Estimator

Estimate how much a framed and sheathed wall panel weighs, so crane and delivery conversations start from a real number.

Wall Effective R-Value Estimator

See how framing lowers the R-value of an insulated stud wall, and what continuous exterior insulation does to it.

Foundation Concrete Calculator

Add up the concrete in footings, foundation walls, pads and a slab, in cubic metres with an ordering allowance.